Construction of a school for 500 students continues in Simferopol
CrimeaPRESS reports:
Today, construction readiness is 20%noted the Chairman of the Government.
According to Yuri Gotsanyuk, a previously concluded contract with the contractor was terminated unilaterally due to violations of the terms of the contract.
As part of the state contract, an inspection of the technical condition of the building, including supporting structures, is carried out. In parallel, preparatory work is being carried out, dismantling the roof, window blocks, walls and parapets, as well as installing temporary access roads.
Completion of construction and installation work is scheduled for December 2026. Receipt of a conclusion on compliance and signing of the facility acceptance certificate is expected in the first quarter of 2027.
source: press service of the Chairman of the Council of Ministers of the Republic of Crimea