Forecast: Underground crossing repairs near Matrosa Koshka promised to be completed by November
CrimeaPRESS reports:
During major repairs, he reports «Sevastopolskaya Gazeta»the supporting reinforced concrete structures are being restored, the entrance groups are being completely reconstructed, the floor and walls of the tunnel part are being finished with natural granite. Storm water drainage, lighting and video surveillance will also be provided. And for people with limited mobility, elevators are provided on both sides, the press service of the department reported.
The contractor intends to complete the work by November, but he has been tasked with opening full-fledged traffic on Geroev Sevastopolya Street by September.
Repairs to the underground crossing at the «Monument to the Sailor Cat» stop began in October 2023. A contract worth 292 million rubles was signed with the Krasnodar company «Dorstroykuban-19». According to its terms, the work must be completed by November 2024. But when starting construction, the contractor promised to complete it by summer — before the start of the tourist season.
The underground passage was built in 1980 with the participation of Sevmorzavod, since one of the plant’s checkpoints was located nearby.
source: «Sevastopolskaya Gazeta»