In Evpatoria, embankments are being put in order
CrimeaPRESS reports:
The head of the administration, Elena Demidova, checked the progress of work on the reconstruction of the embankment. V. Tereshkova and 3 stages of improvement of the Azure Embankment. She announced this on the social network Vkontakte.
According to her, now on the embankment. V. Tereshkova is reinforcing the wave barrier and installing the formwork, developing a lighting trench and plastering the fountain control point, filling the prism of the wave barrier with crushed stone, as well as paving the paths of the park with granite tiles and concreting the promenade slab. At the same time, watering and mowing the lawn is carried out.
At the third stage of the reconstruction of the Azure Embankment, we have already completed the laying of pipes for automatic irrigation and the laying of corrugated pipes for lighting in the promenade area. The parapet along its entire length is already ready for plastering, part of it is already covered with bark beetle. The laying of tiles and the installation of side stone continue.
The work is going on, the result is visible from visit to visit. Like all Yevpatoriya residents, I look forward to strolling along the renovated embankments— Elena Demidova notes.
source: according to the information of the head of the administration of the city of Evpatoria Elena Demidova in the social network «Vkontakte»