In Sevastopol, 82 roads were repaired in six months of this year
Krympress reports:
Within the framework of national and regional projects, 82 out of 100 roads planned for repair this year have already been done. This is more than 80% of the total. The director Stanislav Tamataev reported this to the governor during the hardware meeting the director of the Department of Transport and Development of Road Transport Infrastructure.
The remaining 18 objects will be handed over until the end of September. Among them are roads of regional and inter -municipal significance, as well as intra -quarter driveways, first accepted for balance and included in the repair program. Work is at a good pace,-quoted the press service of the Government of Sevastopol Stanislav Tamataev.
In 2025, 100 objects with a total length of almost 38 km, as well as one bridge structure with a length of 119 linear meters, were repaired. The work is carried out as part of the national project “Infrastructure for Life”.
One of the key areas is the repair of intra -quarter driveways. On behalf of the governor Mikhail Razvozhaev, in 2024, an inventory of the road network, previously not assigned to the balance holders, was carried out. Based on these data in 2025, 20 intra -quarter roads are included in the repair, from which work at 14 facilities has already been completed— said Stanislav Tamataev.
In the framework of cooperation with the Moscow government, four streets are landscaped, two more are in the final stage. Also, within the framework of the national project, there is a repair of the bridge over the Chernaya River. From August 1, movements have already been opened there on two sides, work continues and will be approximately completed in November.
From August 1, a section of the road along Chelnokova Street was blocked in connection with the construction of the road on Antichnaya Avenue. It provides for the creation of a two -lane road 7.5 meters wide with sidewalks, bicycle roads, modern stop complexes, traffic lights and pedestrian crossings. The level of construction readiness as of the beginning of August is 57%, the completion of the work is scheduled for the end of the year, ”said the head of the relevant department.
On behalf of the governor, preparations for road repair in 2026 have already begun.
Source: press service of the Government of Sevastopol