In Simferopol, the reconstruction of the electrical substation «Severnaya»
CrimeaPRESS reports:
In Simferopol, on Kuibyshev Street, the reconstruction of the Severnaya electrical substation is underway. Chairman of the Council of Ministers of the Republic of Crimea Yuri Gotsanyuk spoke about the progress of work.
To date, the first phase of the facility has already been completed. The second phase of the reconstruction of the facility is ongoing. There are almost 60 workers. All necessary work is being done. After construction is completed, two transformers will be able to produce 63 MVA each. Also, a 110 kilovolt cable line is being installed in the Abdala region.— said Yuri Gotsanyuk.
Photo: press service of the Prime Minister of the Republic of Crimea.
News of the Crimea | CrimeaPRESS