In the framework of the dumping to networks in Crimea, about 21.8 thousand households were connected
Krympress reports:
The head of the Republic of Crimea spoke in his Telegram channel about the gasification of the settlements of the republic. According to Sergey Aksyonov, referring to the data of April 1 of this year, about 21.8 thousand households have been connected to the networks from the beginning of the program.
More than 1.1 thousand kilometers of gas supply networks were commissioned. In total, from 2025 to 2028, it is planned to connect 6,570 households— the head of Crimea informed.
Sergei Aksyonov recalled that the total planned amount of financing of the regional gasification program in 2025 is more than 4 billion rubles.
So, today the first houses are connected to the gas in the village of Renaissance of the Kirovsky District.
This was made possible thanks to the construction of inter -settlement and distribution gas pipelines with a total length of more than 15.3 km. The implementation of the project began in September last year as part of the regional program of gasification of settlements of the Republic of Crimea, approved in December 2023. In accordance with the presidential order in the village, the installation of gas pipelines was carried out to the boundaries of the land plotIn, — shared the head of the republic.
Work on the conclusion of contracts for construction and installation works within the borders of the applicants continues. At the moment, 61 applications for a technological connection have been submitted.
Source: Information and press service of the Head of the Republic of Crimea