In Yevpatoria, a new water carrier is being built
Krympress reports:
To date, the monolithic work of the pure water tank with a volume of 12 thousand cubic meters has been completely completed. The percentage of the readiness of the water supply network reaches 95%, the pressure water supply — 90% and the same amount of operator— said Yuri Gotsanyuk.
Work on technical accession to power supply and water supply networks should be completed in October 2025.
During the inspection, a number of comments were recorded regarding the lag from the schedule. In this regard, Yuri Gotsanyuk emphasized the need to take urgent measures to correct the situation.
For timely commissioning of the facility, it is necessary to accelerate the pace of work, increase the number of labor and attract additional special equipment— said the chairman of the Council of Ministers. The implementation of this project is under the control of the leadership of the republic.
Source: press service of the Chairman of the Council of Ministers of the Republic of Crimea