Medical clusters are being built in Sevastopol
Krympress reports:
The governor of Sevastopol Mikhail Razvozhaev, together with the First Deputy General Director of Rostec State Corporation Vladimir Artyakov, held an on-site meeting at the construction site of the ambulance hospital and the medical and diagnostic building of the oncological dispensary.
These are two most important medical facilities for Sevastopol. The head of the city recently discussed the course of work with the Minister of Construction IREK ENVAROVICH FAZULIN: both objects required amendments to projects and additional approval.
I personally control the progress of construction, and today with my colleagues we instructed the facilities and discussed further actions. Initially, according to the project, part of the high -tech equipment planned to be purchased, including in those countries that the supply of their products to Russia was stopped. The alternative was found, but part of the premises had to be redesigned to new equipment parameters. The equipment was agreed by the Department of Health and the Ministry of Health of the Russian Federation; When we leave the examination, we will accelerate the pace of work. Now the construction is actively in those parts of objects that recalculation does not apply,-quoted the press service of the Government of Sevastopol Mikhail Pravozhaev.
On the buildings of the cancer dispensary, there is now reinforcing vertical structures, the installation of formwork and masonry of the external walls. Monolithic work has been completed in the ambulance hospital, now builders are finishing the installation of window blocks and start facade work.
The BSMP building has large metal cross -shaped structures. These are dumping beams — the strengthening necessary for the seismic resistance of the building. They were provided for by the project; Earlier at a meeting of the architectural and art council, it was decided how to formalize them with decorative panels. This will be done during the facade.
Recall that an ambulance hospital is designed for 470 beds. Its structure will include a reception department, a diagnostic block, an operating unit, a hospital, a laboratory unit with auxiliary services and food blocks. The oncological dispensary is designed for 150 beds. The medical facility provides for the diagnostic and operating rooms, the cytological laboratory, a pharmacy and a catering block.
Source: press service of the Government of Sevastopol