Sevastopol is being prepared for winter — the reconstruction of the boiler house on Orlovskaya street is being completed
CrimeaPRESS reports:
The boiler room on Orlovskaya Street serves the adjacent residential area — this is about 30 apartment buildings, the educational center named after. V. D. Revyakina, kindergarten No. 87 and music school No. 7.
Today we inspected the facility, the work is almost completed in full. In the coming days, the contractor will involve the operating organization to inspect all equipment and installations. After that, we prepare documents to send them to Rostekhnadzor. We plan that the paperwork will take us a month and a half, and by the end of November we plan to put the facility into operation , — quotes the press service of the Government of Sevastopol and. about. Director of Capital Construction Department Igor Akhmedov.
Currently, the facility is in the process of installing an asphalt concrete pavement and a gutter, installing a chamber for the heating main and fencing sections, and preparing for hydraulic testing of the heating main.
The boiler house itself is manufactured at the factory, and it is delivered to the facility as ready-made modules that are assembled into a single unit. All engineering networks within the land plot have already been replaced at the facility, a new smoke exhaust system has been completed. A telemetry system has been installed, that is, the operator can remotely fully control the process of the boiler house, all regular and emergency situations, and quickly make decisions, the boiler room is fully dispatched , — emphasizes the director of the contractor company Sergey Besarab.
Reconstruction of the boiler house is carried out by the contractor Delta Stroy Service. The deadline for completion of work under the contract is December 2022 of the year. Contract price – 49, million rubles .
Recall that this year the construction of a gas modular boiler house is also underway instead of the existing one built into a residential building at ul. Bolshaya Morskaya, . The works are planned to be completed before the end of the year.
photo: press service of the Government of Sevastopol
Comments are closed.