Sevastopol was inspected by Deputy Government of the Russian Federation Marat Khusnullin
CrimeaPRESS reports:
During a working visit to Sevastopol, Deputy Prime Minister of the Russian Federation Marat Khusnullin, together with the Governor of Sevastopol Mikhail Razvozhaev, visited key construction sites at Cape Khrustalny. Also during the meeting, topical issues of the development of the region were discussed.
Together with Marat Shakirzyanovich Khusnullin, we examined our key facilities under construction: the Art Museum, the construction site of the Opera and Ballet Theatre, the Choreographic Academy. They discussed the construction of treatment facilities at the Southern WWTP, the progress of work on the implementation of a comprehensive plan to ensure a reliable water supply for Sevastopol and work at large road facilities , the press service of the Sevastopol Government quotes Mikhail Razvozhaev.
According to Marat Khusnullin, the key issue is the fight against losses in networks. It is necessary to deal specifically with the accounting and minimization of such losses.
It is necessary to deal specifically with the accounting and minimization of such losses. It is also important to develop a treatment system, which will provide as many people as possible with clean drinking water , — said Deputy Prime Minister Marat Khusnullin.
Governor of Sevastopol Mikhail Razvozhaev reported on the implementation of measures to reduce losses in water supply networks in the city.
This year alone, we will carry out six more measures to overhaul water supply networks with a total length of 9.6 km. Loss reduction is planned in the amount of 2.38 thousand cubic meters. m / day. In the 63 year, 30 activities were already carried out to overhaul of water supply networks with a total length , km, which made it possible to save drinking water in the amount of 1,63 thousand .cube m / day , — emphasizes Mikhail Razvozhaev.
At the Yuzhny WWTP, construction and installation works are planned to be completed by 06 December 2024 of the year. In March, a positive conclusion was received. FAU «Glavgosexpertiza of Russia» based on the results of engineering surveys. And May — a positive conclusion. FAU «Glavgosexpertiza of Russia» for the construction of a supply collector, a building for mechanical wastewater treatment, a sand trap building, and an administrative building.
As for federal construction projects: the Opera and Ballet Theatre, the Academy of Choreography, the Art Museum, the facilities are being built on schedule, despite the sanctions restrictions.
Completion of construction and installation work on the cultural and educational cluster in Sevastopol is scheduled for December 2023 of the year. Now the task is to resolve the issue of agreeing on the final estimate in connection with the replacement of part of imported building materials with domestic ones and it will be necessary to increase the pace of construction , — said Marat Khusnullin.