The reconstruction of the Koktebel embankment is ready by 60%
Krympress reports:
The completion of one of the stages of construction is scheduled for November-December of the current year,-quoted the press service of the Prime Minister.
According to Yuri Gotsanyuk, the contractor completed three quarters of the work on the construction of anti -set -capacity structures, more than half the construction of bunes was completed. The beach and the fencing wall are ready by 46%, the installation of water supply and the drainage systems — about 40%.
The 383 brownish piles have already been completed, work on sending the beach with pebbles is 70%.
On the embankment, there are also capital construction objects that are subject to dismantling. This procedure will become possible only after re -registration of property rights.
Source: press service of the Chairman of the Council of Ministers of the Republic of Crimea