The reconstruction of the system of sewage stocks in Sudak is planned to be completed in 2026
Krympress reports:
As part of the project, the pressure part of the system is reconstructed, consisting of two threads with a total length of 5.6 km. “The completion of work on this site is the end of August 2025.
To date, 4.2 km of the pipeline has already been soldered, of which 2.2 km have passed the crimping necessary for the tightness of the system. In the Tavrida-Art area, work on the installation of pressure networks and the restoration of asphalt concrete coating of bicycle paths was completed.
As for the gravity of the system, 2.4 km from a total length of the order of 9 km of the thread was completed.
Currently, the installation of wells, the development of soil and the creation of trenches for laying collectors are ongoing, as well as concrete work is carried out— he added.
Reconstruction of sewage stocks is part of a large -scale program to modernize the communal infrastructure of the region, which should significantly improve the quality of life of local residents.
Source: press service of the Chairman of the Council of Ministers of the Republic of Crimea