Villages in Sevastopol continue to be gasified
CrimeaPRESS reports:
In Sevastopol, gasification of villages in the Balaklava region continues under the state program for the socio-economic development of the Republic of Crimea and Sevastopol.
Construction of low-pressure gas pipelines is currently underway in three villages of the Baydar Valley: Rossoshanka, Rodnikovoe and Peredovoe.
In the village of Rossoshanka, work is underway on Tavricheskaya Street. Now the specialists of the contractor company are excavating the soil of the trenches, installing the pipeline and basement inlets, and after completion of the work, the asphalt surface will be completely restored. The total length of the gas pipeline is more than 5 kilometers. Construction and installation work on this site began at the end of October, now 3 units of equipment and 6 workers are involved here, in the future the pace of construction will increase.
In the village of Rodnikovoe, the length of the gas pipeline route exceeds 8 kilometers. As of today, builders have completed laying four kilometers of the route; Specialists also improve the territory in those areas where work has already been completed. It should be noted that along the main street of the village — Kulikova Street — work is planned to be carried out using horizontal directional drilling, that is, without opening the asphalt — this will preserve the road surface.
In the village of Peredovoye, the total length of the gas pipeline is just over 14 kilometers. As of today, about 20% of the work has been completed, 2.5 kilometers of the main pipe have been laid, the contractor is increasing the pace and increasing the volume of work: importing additional materials, developing trenches, and starting work on bends.
At the end of last year, we also signed contracts for the construction of low-pressure gas networks in Ozernoye and Podgornoye. Now in Ozernoye the process of receiving completed construction is underway, and in Podgornoye the landscaping is being completed after the installation of a gas pipeline — according to the schedule of the Russian Ministry of Construction, this facility was supposed to be commissioned by December 2025, but the work was completed ahead of schedule, and we plan to commission the completed construction ahead of schedule– the press service of the Government of Sevastopol quotes the governor of the city, Mikhail Razvozhaev.
Let us remind you that work on gasification of villages began this year, and it is planned to fully complete it in 2025.
source: press service of the Government of Sevastopol