How is the overhaul of the children's choreographic school in Simferopol going?
CrimeaPRESS reports:
Readiness of the object — 70%
This year, 10.4 million rubles have been allocated from the federal and republican budgets for the overhaul of the children’s choreographic school in Simferopol. Construction and installation works are carried out within the framework of the regional project «Cultural Environment» of the national project «Culture». The regional office of the Main Directorate for the Implementation of National Projects told about the progress of the overhaul.
Currently, the school is changing the heating, installation of engineering networks has been carried out. Finishing work is being completed at the facility, preparatory work is underway for painting the walls. The decorative plastering of the facade has been completed, painting work has begun. False ceilings and lighting are installed inside the building. Toilets and showers are being tiled— reported in the Main Directorate.
The installation of floors and tamping of the base for pouring the screed has already been carried out, as well as preparatory finishing work on walls and ceilings: sealing holes, grooves in walls and partitions, leveling internal surfaces.
The school will install lamps with an emergency uninterruptible power supply system. In the event of a power outage, they will be able to work for more than two hours.
Work at the facility began on March 1 of the current year and is being carried out in accordance with the approved schedule for the production of measures. The contracting organization plans to hand over the renovated children’s choreographic school earlier than the deadline set by the contract.