Crimean News
News of Crimea - The latest news of Crimea today. Events and incidents, economics and finance, sports, science, culture, resorts, society and politics in Crimea. Crimean news for the last day. Sevastopol News

The bridge in Inkerman will be repaired before the end of THIS YEAR

CrimeaPRESS reports:

In social networks and a number of media there were publications that the deadline for the completion of the overpass in Inkerman was postponed to the end 2023 of the year. Today Pavel Ieno, Director of the Department of Transport and Road Infrastructure of Sevastopol, visited the site. He said that the reconstruction of the overpass (the bridge in Inkerman) is planned to be completed on time — before the end 2022 of the year . An additional agreement on the transfer of limits was signed with the contractor. According to the document, for the work that will be completed this year, the company will receive funds at the beginning of the next.

Мост в Инкермане отремонтируют до конца ЭТОГО ГОДА

We monitor the situation at the facility daily. As for the technical parameters: the overpass with a length of 36, 5 meters provides for two lanes for vehicles and two pedestrian networks of 1, 5 meters. The total width of the overpass is , 5 meters. To date, work is underway on the arrangement of bored piles — in total, the project provides for 36 pieces, 20 of which have already been completed , – said Pavel Yen.

Мост в Инкермане отремонтируют до конца ЭТОГО ГОДА

According to him, workers at the facility have already shifted electrical communications and are replacing water supply networks. Reconstruction is progressing ahead of schedule.

Мост в Инкермане отремонтируют до конца ЭТОГО ГОДА

Pavel Ieno also spoke about the progress of work on the Yalta Ring. Thus, the contracting organization «VAD» has already launched traffic along the main passage through the tunnel.

We expect that at the end of September — beginning of October the contractor will completely hand over the traffic interchange with all adjuncts to it. It will become a little easier , — emphasized the head of the relevant department.

Recall that during the reconstruction of the overpass in Inkerman, a detour along Yablochkova Street is preserved. Contractor provides traffic regulation from 6: 00 to 11: 00 in manual mode. The railway communication was not suspended — the work is carried out in parallel with the movement of all trains that run towards Sevastopol.

339307

Мост в Инкермане отремонтируют до конца ЭТОГО ГОДА339307Photo: press service of the Government of Sevastopol.339304

Comments are closed.

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More

Privacy & Cookies Policy